K.D. Stahl Construction Group Inc. Project Update - framing, electrical, mechanical, plumbing, and fire sprinklers for the showroom at Bedrosian Tile & Stone by Kraig Stahl

With the concrete walls up and our roof structure in place, we are now framing the showroom and our electrical, fire sprinkler, plumbing and mechanical subcontractors are in full production mode. The parking lot is being graded as well and we will share images of the progress on the next update. 

K.D. Stahl Construction Group Inc. San Diego's Leading Commercial General Contractor - Bedrosian Tile & Stone Ground up New Construction

Bedrosian Tile & Stone
Tenant

Gensler
Architect

Dan Dickey
Project Manager

Chris Cherry
Superintendent

Scope of Work:

The new construction project will entail a 30,000 Sq.Ft. tilt-up building, with 6,500 Sq. Ft. of showroom, offices, and site work.

K.D. Stahl Construction Group Inc. San Diego's Leading Commercial General Contractor - Bedrosian Tile & Stone Ground up New Construction
K.D. Stahl Construction Group Inc. - Bedrosian Tile & Stone Ground up New Construction
K.D. Stahl Construction Group Inc. - Bedrosian Tile & Stone Ground up New Construction
K.D. Stahl Construction Group Inc. San Diego's Leading Commercial General Contractor - Bedrosian Tile & Stone Ground up New Construction

K.D. Stahl Construction Group Inc - Ionis Fitness Center Project Update by Kraig Stahl

The Ionis Fitness Center built for Ionis Pharmaceutical is completed and doors are open to the staff of Ionis. 

 
K.D. Stahl Construction Group Inc. - Ionis Fitness Center Ground up Construction

Ionis Pharmaceuticals
Tenant

DGA
Architect

BWE
Structural / Civil Engineer

MPE Engineers
Electrical Engineer

DEC Engineers
Mechanical / Plumbing Engineer

NERI Landscape Architecture 
Landscape Architect

Location:

2855 Gazelle Court
Carlsbad, CA 92010

Scope of Work:

This project consists of the partial demolition of an existing paved parking lot and associated site improvements and the construction of a new one story 5,475 s.f. employee fitness building, outdoor sports court, recreational green space, and associated site improvements.

K.D. Stahl Construction Group Inc. - Ionis Fitness Center
K.D. Stahl Construction Group Inc. - Ionis Fitness Center

Interior finishes 

K.D. Stahl Construction Group Inc. - Ionis Fitness Center
K.D. Stahl Construction Group Inc. - Ionis Fitness Center

Past to Present

K.D. Stahl Construction Group Inc. - Ionis Fitness Center Ground up Construction
K.D. Stahl Construction Group Inc. - Ionis Fitness Center

CMU Walls Stood 

K.D. Stahl Construction Group Inc. - Ionis Fitness Center Ground up Construction
K.D. Stahl Construction Group Inc. - Ionis Fitness Center Ground up Construction
K.D. Stahl Construction Group Inc. - Ionis Fitness Center Ground up Construction

Pre Slab Pour

K.D. Stahl Construction Awarded Broadway Apartments by Kraig Stahl

Broadway Apartments 

Location: 
2828 Broadway
San Diego, CA 92102

 

The Team

Project Manager
Bob Turner

Superintendent
Bill Shepard

 

Architect
Sillman Wright Architects
Brett Tullis AIA LEED AP
7515 Metropolitan Dr. Suite #400
San Diego, CA. 92108
T: 619.294.7515
btullis@sillmanwright.com

Engineering
Naraghi Engineering
Tom Naraghi
16340 Chaparral Way, Bldg. B
Poway, Ca 92064
T: 858.435.4877
tomnaraghi@aol.com

Civil
K & S Engineering, INC.
Hossein Zorromodi
7801 Mission Center Court, Suite 100
San Diego, CA 92108
T: (619) 296-5565
h-zorromodi@ks-engr.com

Electrical
FARD Engineers
Mike Bowden
3550 Camino del Rio North, Suite 204
San Diego, CA 92108
T: (619) 235-0022
mike@fard.com


Scope:

The 34 Multi-family dwellings consist of 20 One bedroom Apartments and 14 Studio Apartments. This apartment building is 3 story above grade and a basement parking structure.


Plumbing
FARD Engineers
Matt Constant
3550 Camino del Rio North, Suite 204
San Diego, CA 92108
T: (619) 235-0022
matt@fard.com

Mechanical
FARD Engineers
Bijan Nikravesh
3550 Camino del Rio North, Suite 204
San Diego, CA 92108
T: (619) 235-0022
bijan@fard.com

Construction management company
Kirt Gilliland
17898 Corazon Place
San Diego, CA 92127
Mobile 619-977-8046 | Office 619-402-1886
e-mail kirt@gillilandcm.com

K.D. Stahl Construction Awarded Rady Children’s - Children’s Primary Care Medical Group Encinitas Tenant Improvement by Sean Stahl

 
 

Children’s Primary Care Medical Group, Encinitas

Location: 
499 El Camino Real, Suite 100
Encinitas, Ca 92024

 

The Team 

Project Manager
Bob Turner

Superintendent
Andrew Castillo

Architect
Reilly and Associates


Scope:
Complete interior demolition of an existing 8,071 SF 1 Story medical office and new tenant improvement for a medical office practice that specializes in children’s primary care.


K.D. Stahl Construction Project Update: UCSD Pub and Event Space Renovation by Sean Stahl

We have completed our portion of the UCSD Pub extension. We gave the pub a new handicap access ramp, new front patio and the roll up doors for the future restaurant build out. 


Exterior Renovation Construction 

A large portion of the UCSD Pub Extension included an exterior patio and additional exterior venue space as well new handicap ADA ramps where designed and built to spec for the new entrance and fire escape ramp in the back.

K.D. Stahl Construction Group Inc. - UCSD Pub Renovation Construction
K.D. Stahl Construction Group Inc. - UCSD Pub & Music Venue Renovation
K.D. Stahl Construction Group Inc. - UCSD Pub Music Venue Renovation
K.D. Stahl Construction Group Inc. - UCSD Pub Music Venue Renovation
 

Interior Renovation Construction

New glass panel roll up doors and finishes in the UCSD Pub & Venue. 

ucsd-pub-1.jpg
ucsd-pub-2.jpg

K.D. Stahl Construction Progress Update - Bunker Hill Office Space - Tenant Improvement by Sean Stahl

The Bunker Hill Office Space Tenant Improvement is complete and tenants have moved in. Check out our final project photos to see how great the office space turned out. 

Located at:
3033 Bunker Hill St.
San Diego, Ca 92109


ARCHITECTURAL DESIGN
Prismática Design

ELECTRICAL
Randall Lamb

PLUMBING & MECHANICAL
Randall Lamb

SCOPE OF WORK:
Tenant improvement of existing 3 story, 26,000 sf. office building with basement in Pacific Beach, San Diego CA. The location is destined to be the headquarters of Fortune Builders, a premier real estate investing education company. The project includes the build out of office spaces, conference rooms, class rooms, a film studio and a cafeteria.

K.D. Stahl Construction Group Inc. - Bunker Hill Tenant Improvement Construction

Project Update Photo Archive

K.D. Stahl Construction - Bunker Hill Renovation Project Update

blog update: 03/15/17


Blog update 01/10/17

 
 

K.D. Stahl Construction Group Inc - Standing Walls at Bedrosian Tile & Stone by Sean Stahl

Concrete panels flew up last week at Bedrosian Tile & Stone on Miramar Road. Big changes are occurring! Next phase we will be setting trusses and roof structure. Once the structure is finished we will begin the interior phase. 

K.D. Stahl Construction Group Inc. - Bedrosian Tile & Stone Ground up New Construction

Bedrosian Tile & Stone
Tenant

Gensler
Architect

Dan Dickey
Project Manager

Chris Cherry
Superintendent

Scope of Work:

The new construction project will entail a 30,000 Sq.Ft. tilt-up building, with 6,500 Sq. Ft. of showroom, offices, and site work.

K.D. Stahl Construction Group Inc. - Bedrosian Tile & Stone Ground up New Construction
K.D. Stahl Construction Group Inc. - Bedrosian Tile & Stone Ground up New Construction