K.D. Stahl Construction Progress Update: cCare Nordahl Medical Centre Tenant Improvement by Sean Stahl

 

There is a lot happening at the cCare Nordahl Medical Centre. Framing is complete, Drywall is hung and being taped and hot coated while some sections are in the finished coat phase. We currently have Greater San Diego Air Conditioning  on site installing all the HVAC systems, some of which is the AAON system for the future pharmacy. 

 

We have just begun the cCare tenant Improvement at Nordahl Medical Centre. Framing is underway, here are a few photos of the detailed framing going in right now.   

Location:

838 Nordahl Road, Suite 300
San Marcos, Ca 92069

blog update: 03/09/17


Update 01/27/17

nordahlmedicalcentre

Scope of work:

14,000 sf Cancer Care Medical Facility, featuring, dr. offices, exam rooms, infusion bays, compounding pharmacy and a PET/CT scanner.

 

Team:

 

Client
Nordahl Medical Centre Inc. 

Space Planner
DesignCorp

HVAC Design
Harrington Mechanical Design Inc.

Electrical Design
Nutter Electrical Design Inc.

 

Project Manager
Bob Turner | bobt@kdstahl.com

Superintendent
Bob Broadburst | robertb@kdstahl.com

 
 
 
 

K.D. Stahl Construction Project Update: UCSD Pub and Event Space Renovation by Sean Stahl

 

A lot is changing at the UCSD Pub and Event Space as we push toward our completion date. below are a few images and notes on the current status of the project

 

The interior concrete ADA ramp and infills are poured and finished. All the interior walls are framed to the new floor plan. All mechanical, electrical and plumbing is installed. 

 

The interior and exterior demo is complete and the new openings for the entrance are framed. There will be two roll up doors in the main entrance which will give the new pub an open environment for the students. 

 

The new entrance to the concert venue is one of the biggest transformations on site thus far. The concrete walls and seats are poured and are now ready for the steps and CMU wall to be built on the upper section of the ramp. The exterior bar slab is poured and structure has been framed, sheeted, wrapped and ready for roofing.


Thanks for keeping updated on our progress at the UCSD Pub & Event Space, We will be updating you as the projects moves along...

 

 

 

K.D. Stahl Construction Finalized Rancho Vista Community Church by Sean Stahl

All inspections are signed off at the new home of Rancho Vista Community Church and they are now open for service. 

Located at:
2088 Otay Lakes Road
Chula Vista, CA 91913

Team:

Owner:
Rancho Vista Covenant Church

Architect:
Duane Butler

Mechanical Engineer:
Diana Irwin Designs

Scope of Work: 

Tenant improvements to existing office building. Build out of worship center with education rooms on 1st and 2nd floors.  Provide ADA compliant Men's and Women's restrooms and the addition of a cafe area.

 

K.D. Stahl Construction Awarded New Construction of Ionis Fitness Center by Sean Stahl

We are in our preliminary stages and are set to start the new construction of Ionis Fitness Center for Ionis Pharmaceutical . Stay tuned as we will be updating this blog as the project moves forward. 

Location:

2855 Gazelle Court
Carlsbad, CA 92010

 
ionisrendering

Ionis Pharmaceuticals
Tenant

DGA
Architect

BWE
Structural / Civil Engineer

MPE Engineers
Electrical Engineer

DEC Engineers
Mechanical / Plumbing Engineer

NERI Landscape Architecture 
Landscape Architect

Scope of Work:

This project consists of the partial demolition of an existing paved parking lot and associated site improvements and the construction of a new one story 5,475 s.f. employee fitness building, outdoor sports court, recreational green space, and associated site improvements.

K.D. Stahl Construction Finalized Mountain Health Community Center by Sean Stahl

Our team at K.D. Stahl Construction Group Inc. has finished the tenant improvement of Mountain Health Community Heights Family Medicine Center. 

Located at:
4690 El Cajon Blvd.
San Diego, CA 92115

Architectural Design
Thiessen Sci-Tech Architecture

Structural
GSSI Structural Engineers

M.E.P.
Pro Engineering Consulting, Inc.

 

Scope of work:
Tenant Improvement of non-profit medical and dental community center building. Existing shell to receive new stucco, new store front entry to be tiled and all new storefront glazing. Inside space was completely built out to accommodate and comply with all regulations necessary for medical and dental occupancy. The exterior hardscape was resurfaced and new concrete entry way poured per site plans.  
 

K.D. Stahl Construction Awarded UCSD Pub Shell & Event Space Renovation by Sean Stahl

We are set to start the renovation of University of California, San Diego's Pub & Event Space. Project is underway, stay tuned as we will be documenting the progress of this project as it moves along.  

Located at:
9500 Gilman Drive
La Jolla, CA 92093

Civil Engineer
Atlas Civil Design

Structural Engineer
KPFF Consulting Engineers

Landscape Architect
David Reed Landscape Architects

 

Scope of Work:
The pub side will encompass demolition of existing walls, flooring, kitchen equipment, light fixtures and associated infrastructure. The new work for the pub is to prepare the space as a warm shell including mechanical, electrical, plumbing work, for a future vendor build-out. New walls, doors (interior and exterior), and new exterior patio areas with low retaining walls, metal gate and guardrails for dining will be constructed as part of this work. Demolition of existing bay window and walls to make the front elevation more transparent by use of two aluminum and glass fold-up doors. A new steel awning sunshade over the two fold-up doors. 

The stage venue will be a full upgrade and renovation to the space for the University to run as a separate occupant. The interior demolition consists of removing walls, concrete ramp and stairs, light fixtures, floors, flooring and other related infrastructure. The new work consists of creating a new concrete path from the main campus walkway, accessible ramps and stairs. A new storage room will be added in the center of the building with access of the shared corridor. The new interior work will provide flooring, accessible ramp, doors, windows, and associated infrastructure. The existing light fixtures will be replaced with LED light fixtures. The existing men's and women's restrooms, which will be shared by both venues, will be upgraded to current ADA standards where applicable. A new patio bar space with fold-up aluminum and glass doors will be constructed attaching to the east elevation. 

New Construction of Conrad Prebys Boys & Girls Club by Sean Stahl

K.D. Stahl Construction Group has been awarded the new construction & remodel of Conrad Prebys Ramona Branch Addition. Located in the heart of Ramona, California.

Located at: 
622 E Street Ramona Ca, 92065

Architect
Jeff Katz Architecture

Electrical
Elen Consulting

Mechanical & Plumbing
McParlane & Associates

Civil Engineer
Michael Baker International

Landscape
Parterre

Structural Engineer
Orie 2 Engineering

Scope of Work:

2455 sq. ft. addition of multipurpose room, kitchen, storage, hallway, women's and men's restroom, remodeling existing women's and men's restrooms and replacing bathroom partitions. 

 
 

Project Update: Rancho Vista Community Church by Sean Stahl

The 3177sq. ft. two story church tenant improvement for Rancho Vista Community Church is well underway. We are currently in the framing, drywall and MEP rough-in stages.

located at:
2088 Otay Road Ste. 101
Chula Vista, Ca. 91915

Below is the sample material and design for the new church doors leading into the service room. 

 We are on schedule to have this Church ready for this years Christmas service.

K.D. Stahl Construction Project Update: Toussaint Academy of San Diego by Sean Stahl

We've moved into the second phase at Toussaint Academy in the heart of San Diego, Ca. We are currently, replacing the window cladding with a black finished metal and will be removing the interior window film to be replaced with an energy efficient retrofit film. 

The glazers hard at work replacing the window cladding.

New window cladding to the right and the old cladding on the left.

Toussaint Academy's new exterior look is almost there. Once the new energy efficient retrofit window film is installed, this academy will be presenting well.

Project update: Phase one is almost complete as the exterior of Toussaint Academy gets repainted. 

An image as we near finishing painting the interiors and exterior of Toussaint Academy of the Arts and Sciences in downtown San Diego.

An image as we near finishing painting the interiors and exterior of Toussaint Academy of the Arts and Sciences in downtown San Diego.